Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-16-42 03-4F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 03-PLA-80-31.1/31.9 NONE Progress payment No. 003 Payment period ending: 09-20-15 BALDWIN CONTRACTING CO., INC. DBA KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 984,425.59 106,892.54 2. a. Extra Work 74,260.38 74,260.38 b. Adustment Comp. 6,650.00 17,250.00 3. Materials on Hand 4. Earned Subject to Retention 1,065,335.97 198,402.92 5. Mobilization 6. Total Work Completed 1,065,335.97 7. Deductions -7,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,058,335.97 196,402.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,402.92