Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-039-13-38 03-4F8104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-GLE-32-L0.0/0.9 NONE Progress payment No. 003 Payment period ending: 12-21-20 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 594,930.49 48,700.05 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 594,930.49 48,700.05 5. Mobilization 6. Total Work Completed 594,930.49 7. Deductions -20,000.00 -19,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 574,930.49 29,700.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,700.05