Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-272-10-21 03-4F8404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-50-70.6/70.6 HSNH-P050(144) Progress payment No. 012 Payment period ending: 05-26-20 Q & D CONSTRUCTION INC PO BOX 10865 RENO NV 89510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,930,986.77 20,436.40 2. a. Extra Work 130,332.07 0.00 b. Adustment Comp. -11,613.10 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,049,705.74 20,436.40 5. Mobilization 412,019.58 0.00 6. Total Work Completed 4,461,725.32 7. Deductions 0.00 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,461,725.32 50,436.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,436.40