Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-301-15-34 03-4H0304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED SSTG-000C(496) Progress payment No. 003 Payment period ending: 10-03-19 CENTRAL STRIPING SERVICES INC. 3489 LUYUNG DRIVE RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 628,466.97 181,416.80 2. a. Extra Work 349,274.99 349,022.99 b. Adustment Comp. 10,000.00 10,000.00 3. Materials on Hand 4. Earned Subject to Retention 987,741.96 540,439.79 5. Mobilization 6. Total Work Completed 987,741.96 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 22,018.43 c. Reduction after 95% Comp. 9. Total pay to Contractor 977,741.96 552,458.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 552,458.22