Dept. of Trans. PROGRESS Serial No. Contract No. 24-234-08-08 03-4H0704 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 39% Location: Federal Project: 03-NEV-20-R12.0/20.0 ACNH-P020(203) Progress payment No. 005 Payment period ending: 08-20-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,992,525.48 5,316,878.81 2. a. Extra Work 284,758.93 72,554.07 b. Adustment Comp. -249,344.12 10,858.08 3. Materials on Hand 179,618.00 179,618.00 4. Earned Subject to Retention 14,207,558.29 5,579,908.96 5. Mobilization 2,016,777.00 100,838.85 6. Total Work Completed 16,044,717.29 7. Deductions -30,499.30 -20,024.97 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,193,835.99 5,660,722.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,660,722.84