Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-11-02 03-4H0704 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 51% Location: Federal Project: 03-NEV-20-R12.0/20.0 ACNH-P020(203) Progress payment No. 006 Payment period ending: 09-20-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,912,836.80 1,920,311.32 2. a. Extra Work 364,223.49 79,464.56 b. Adustment Comp. -249,344.12 0.00 3. Materials on Hand 178,001.00 -1,617.00 4. Earned Subject to Retention 16,205,717.17 1,998,158.88 5. Mobilization 2,016,777.00 0.00 6. Total Work Completed 18,044,493.17 7. Deductions -30,499.30 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,191,994.87 1,998,158.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,998,158.88