Dept. of Trans. PROGRESS Serial No. Contract No. 19-113-11-45 03-4H1504 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 0% Location: Federal Project: 03-YUB-70-0.0 NONE Progress payment No. 004 Payment period ending: 04-20-19 NORDIC INDUSTRIES, INC 1437 FURNEAUX RD OLIVEHURST CA 95961 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 541,379.19 69,425.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 541,379.19 69,425.47 5. Mobilization 6. Total Work Completed 541,379.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 541,379.19 69,425.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,425.47