Dept. of Trans. PROGRESS Serial No. Contract No. 18-354-09-15 03-4H4404 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 100% Location: Federal Project: 03-PLA-80-50.7/50.8 NONE Progress payment No. 002 Payment period ending: 12-20-18 LORANG BROTHERS CONSTRUCTION INC. 1175 S. AUBURN ST COLFAX CA 95713 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 717,290.65 52,481.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 717,290.65 52,481.34 5. Mobilization 6. Total Work Completed 717,290.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 717,290.65 52,481.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,481.34