Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-259-14-01 03-4H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-65 HSST-000C(502) Progress payment No. 003 Payment period ending: 07-28-20 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,739,221.90 133,447.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,739,221.90 133,447.40 5. Mobilization 6. Total Work Completed 1,739,221.90 7. Deductions -57,000.00 -57,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,682,221.90 76,447.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,447.40