Dept. of Trans. PROGRESS Serial No. Contract No. 24-235-09-48 03-4H5814 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 97% Location: Federal Project: 03-SAC-5-27.6/29.5 ACIM-056(360) 03-SAC-5-30.4/34.3 Progress payment No. 015 Payment period ending: 08-20-24 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,359,324.44 2,844,438.63 2. a. Extra Work 595,864.13 60,084.73 b. Adustment Comp. 140,840.50 0.00 3. Materials on Hand 139,950.00 -957,065.00 4. Earned Subject to Retention 24,235,979.07 1,947,458.36 5. Mobilization 2,868,000.00 0.00 6. Total Work Completed 26,964,029.07 7. Deductions -19,000.00 -17,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,084,979.07 1,930,458.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,930,458.36