Dept. of Trans. PROGRESS Serial No. Contract No. 25-143-11-03 03-4H6004 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 28% Location: Federal Project: 03-PLA-49-R8.7/R10.6 SNHG-P049(190) Progress payment No. 014 Payment period ending: 05-20-25 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,894,403.32 1,583,464.04 2. a. Extra Work 1,291,108.18 301,084.67 b. Adustment Comp. -24,230.00 0.00 3. Materials on Hand 251,935.00 -59,978.00 4. Earned Subject to Retention 9,413,216.50 1,824,570.71 5. Mobilization 2,280,000.00 0.00 6. Total Work Completed 11,441,281.50 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,691,216.50 1,822,570.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,822,570.71