Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-07-55 03-4H6004 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 63% Location: Federal Project: 03-PLA-49-R8.7/R10.6 SNHG-P049(190) Progress payment No. 017 Payment period ending: 08-20-25 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,516,445.04 1,973,912.38 2. a. Extra Work 2,028,948.82 701,028.81 b. Adustment Comp. 209,614.65 124,671.19 3. Materials on Hand 110,545.91 -82,988.98 4. Earned Subject to Retention 15,865,554.42 2,716,623.40 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 18,155,008.51 7. Deductions -10,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,255,554.42 2,714,623.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,714,623.40