Dept. of Trans. PROGRESS Serial No. Contract No. 20-142-11-11 03-4H6604 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 55% Location: Federal Project: 03-PLA-80-32.7/33.0 NONE Progress payment No. 002 Payment period ending: 05-20-20 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 730,769.45 609,761.23 2. a. Extra Work 26,170.00 26,170.00 b. Adustment Comp. 13,325.71 13,325.71 3. Materials on Hand 4. Earned Subject to Retention 770,265.16 649,256.94 5. Mobilization 60,000.00 15,000.00 6. Total Work Completed 830,265.16 7. Deductions -7,000.00 -7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 823,265.16 657,256.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 657,256.94