Dept. of Trans. PROGRESS Serial No. Contract No. 18-325-09-29 03-4H7104 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 47% Location: Federal Project: 03-VAR-89-1.8/16.3 NONE Progress payment No. 001 Payment period ending: 11-20-18 GRANITE CONSTRUCTION COMPANY 1900 GLENDALE AVE SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 352,348.63 352,348.63 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 352,348.63 352,348.63 5. Mobilization 6. Total Work Completed 352,348.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 352,348.63 352,348.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 352,348.63