Dept. of Trans. PROGRESS Serial No. Contract No. 19-239-08-12 03-4H8304 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 0% Location: Federal Project: 03-BUT-32-0.0/37.7 NONE Progress payment No. 012 Payment period ending: 08-20-19 BALDWIN CONTRACTING CO INC 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 13,590,732.57 366,043.71 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 13,590,732.57 366,043.71 5. Mobilization 6. Total Work Completed 13,590,732.57 7. Deductions -10,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,580,732.57 373,043.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 373,043.71