Dept. of Trans. PROGRESS Serial No. Contract No. 24-201-11-08 03-4H88U4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 14% Location: Federal Project: 03-BUT-32-0.3/5.0 HSNH-P032(50) Progress payment No. 011 Payment period ending: 07-20-24 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,686,631.99 25,245.00 2. a. Extra Work 704,637.12 0.00 b. Adustment Comp. 84,909.54 0.00 3. Materials on Hand 411,524.50 -21,760.00 4. Earned Subject to Retention 5,887,703.15 3,485.00 5. Mobilization 1,258,750.00 0.00 6. Total Work Completed 6,734,928.65 7. Deductions -9,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,137,453.15 1,485.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,485.00