Dept. of Trans. PROGRESS Serial No. Contract No. 25-112-08-00 03-4H8904 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 30% Location: Federal Project: 03-ED-50-75.4/8.0 HSNH-P050(157) Progress payment No. 008 Payment period ending: 04-20-25 ST FRANCIS ELECTRIC LLC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,710,182.84 6,000.00 2. a. Extra Work 67,962.44 0.00 b. Adustment Comp. 3. Materials on Hand 509,279.40 509,279.40 4. Earned Subject to Retention 6,287,424.68 515,279.40 5. Mobilization 1,425,000.00 0.00 6. Total Work Completed 7,203,145.28 7. Deductions 0.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,712,424.68 518,279.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 518,279.40