Dept. of Trans. PROGRESS Serial No. Contract No. 26-170-07-02 03-4H8904 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 67% Location: Federal Project: 03-ED-50-75.4/8.0 HSNH-P050(157) Progress payment No. 014 Payment period ending: 06-20-26 ST FRANCIS ELECTRIC LLC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,134,440.12 4,017,046.23 2. a. Extra Work 76,096.94 8,134.50 b. Adustment Comp. 62,051.35 0.00 3. Materials on Hand 89,532.00 -3,372,840.91 4. Earned Subject to Retention 16,362,120.41 652,339.82 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 17,772,588.41 7. Deductions -4,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,858,120.41 653,339.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 653,339.82