Dept. of Trans. PROGRESS Serial No. Contract No. 23-086-14-26 03-4J1804 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 13% Location: Federal Project: 03-BUT-99-56.0/5.6 NONE Progress payment No. 001 Payment period ending: 03-20-23 DESILVA GATES CONSTRUCTION,LLC 11555 DUBLIN BLVD DUBLIN, CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 40,097.95 40,097.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 40,097.95 40,097.95 5. Mobilization 6. Total Work Completed 40,097.95 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,097.95 30,097.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,097.95