Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 26-265-07-46 03-4J4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-5712-0.0 NONE Progress payment No. 004 Payment period ending: 07-02-26 GLOBE ENGINEERING DEVELOPMENT 2002 ELIJAH ST FAIRFILED CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 898,500.00 52,000.50 2. a. Extra Work 43,780.03 43,780.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 942,280.03 95,780.53 5. Mobilization 6. Total Work Completed 942,280.03 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 932,280.03 85,780.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,780.53