Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-11-51 03-4J8704 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 62% Location: Federal Project: 03-VAR NONE Progress payment No. 002 Payment period ending: 04-20-24 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 582,843.53 142,218.43 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 582,843.53 142,218.43 5. Mobilization 6. Total Work Completed 582,843.53 7. Deductions -8,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 574,843.53 134,218.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,218.43