Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-11-52 03-4M0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 56% 03-SIE-49-0.6/2.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-17-12 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 199,654.20 112,743.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 199,654.20 112,743.80 5. Mobilization 22,800.00 4,800.00 6. Total Work Completed 222,454.20 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 217,454.20 112,543.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,543.80