Dept. of Trans. SEMI-FINAL Serial No. Contract No. 14-066-09-30 03-4M1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-BUT-32-11.3/R15.5 Federal Project: MTCE Progress payment No. 05 Payment period ending: 10-31-13 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,827,497.25 7,481.25 2.a. Extra Work 32,284.05 0.00 b. Adjustment Comp. -2,050.00 -2,050.00 3. Materials on Hand 4. Earned Subject to Retention 1,857,731.30 5,431.25 5. Mobilization 6. Total Work Completed 1,857,731.30 7. Deductions -13,160.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,844,571.30 5,431.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,431.25