Dept. of Trans. PROGRESS Serial No. Contract No. 17-005-10-10 03-4M2004 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 54% Location: Federal Project: 03-COL-5-R22.3 NONE Progress payment No. 005 Payment period ending: 12-20-16 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,534.66 59,153.76 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 221,534.66 59,153.76 5. Mobilization 58,900.00 0.00 6. Total Work Completed 280,434.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 280,434.66 59,153.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,153.76