Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-152-08-41 03-4M2004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-COL-5-R22.3 NONE Progress payment No. 006 Payment period ending: 04-14-17 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,982.16 447.50 2. a. Extra Work 292,324.13 292,324.13 b. Adustment Comp. 10,406.30 10,406.30 3. Materials on Hand 4. Earned Subject to Retention 524,712.59 303,177.93 5. Mobilization 62,000.00 3,100.00 6. Total Work Completed 586,712.59 7. Deductions -31,000.00 -31,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 555,712.59 275,277.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,277.93