Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-15-30 03-4M4204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 83% 03-SIE-49-31.0/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-18-12 AIS CONSTRUCTION COMPANY 1110 EUGENIA PLACE, SUITE 200 CARPINTERIA CA 93013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 170,770.00 130,490.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 170,770.00 130,490.00 5. Mobilization 6. Total Work Completed 170,770.00 7. Deductions -8,000.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 162,770.00 122,490.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,490.00