Dept. of Trans. PROGRESS Serial No. Contract No. 13-234-11-56 03-4M5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 88% 03-BUT-99-13.0/20.6 Federal Project: STP-P099(566) Progress payment No. 02 Payment period ending: 08-20-13 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,527,841.90 370,632.00 2.a. Extra Work b. Adjustment Comp. -17,363.72 -12,863.72 3. Materials on Hand 4. Earned Subject to Retention 1,510,478.18 357,768.28 5. Mobilization 63,500.00 0.00 6. Total Work Completed 1,573,978.18 7. Deductions -7,000.00 -7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,566,978.18 350,768.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 350,768.28