Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-11-30 03-4M5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 37% 03-ED-50-18.1/19.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-18-13 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 578,313.13 578,313.13 2.a. Extra Work b. Adjustment Comp. -17,247.00 -17,247.00 3. Materials on Hand 4. Earned Subject to Retention 561,066.13 561,066.13 5. Mobilization 6. Total Work Completed 561,066.13 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 561,066.13 561,066.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 561,066.13