Dept. of Trans. FINAL Serial No. Contract No. 13-277-08-39 03-4M5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-18.1/19.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-02-13 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 721,891.21 0.00 2.a. Extra Work 6,690.76 0.00 b. Adjustment Comp. -18,856.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 709,725.93 0.00 5. Mobilization 6. Total Work Completed 709,725.93 7. Deductions 0.00 21,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 709,725.93 21,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,000.00