Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-14-48 03-4M5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 66% 03-SAC-160-R44.5/47.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-18-14 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD STE 260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 711,825.96 71,743.16 2.a. Extra Work b. Adjustment Comp. 39,333.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 751,159.41 71,743.16 5. Mobilization 115,000.00 5,750.00 6. Total Work Completed 866,159.41 7. Deductions -880.00 41,633.55 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 865,279.41 119,126.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,126.71