Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-09-20 03-4M5804 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 100% Location: Federal Project: 03-SAC-160-R44.5/47.1 NONE Progress payment No. 004 Payment period ending: 05-20-15 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD STE 260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 747,423.96 35,598.00 2. a. Extra Work b. Adustment Comp. 39,333.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 786,757.41 35,598.00 5. Mobilization 115,000.00 0.00 6. Total Work Completed 901,757.41 7. Deductions -880.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 900,877.41 35,598.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,598.00