Dept. of Trans. PROGRESS Serial No. Contract No. 12-265-11-47 03-4M6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 70% 03-PLA-80-44.8/49.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-17-12 INTERSTATE IMPROVEMENT INC P O BOX 8 FARIBAULT MN 55021 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 280,816.90 280,816.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 280,816.90 280,816.90 5. Mobilization 114,375.00 114,375.00 6. Total Work Completed 395,191.90 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 395,191.90 395,191.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 395,191.90