Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-077-11-57 03-4M6104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-80-28.0 NONE Progress payment No. 012 Payment period ending: 08-14-15 C C MYERS INC 3286 FITZGERALD RD RANCHO CORDOVA CA 957426811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,694,738.50 0.00 2. a. Extra Work 167,676.51 70,241.99 b. Adustment Comp. 4,595.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,867,010.76 70,241.99 5. Mobilization 194,000.00 0.00 6. Total Work Completed 2,061,010.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,061,010.76 70,241.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,241.99