Dept. of Trans. PROGRESS Serial No. Contract No. 15-173-11-44 03-4M7304 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 86% Location: Federal Project: 03-SAC-51-2.6/R44.7 NONE Progress payment No. 008 Payment period ending: 06-20-15 WEST COAST STRUCTURES, INC DBA WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 277,765.63 61,915.53 2. a. Extra Work 110,118.44 2,903.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 387,884.07 64,819.28 5. Mobilization 93,822.86 0.00 6. Total Work Completed 481,706.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -6,481.93 -6,481.93 c. Reduction after 95% Comp. 9. Total pay to Contractor 475,225.00 58,337.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,337.35