Dept. of Trans. PROGRESS Serial No. Contract No. 13-234-12-09 03-4M7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 03-SAC-5-22.0/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-13 INDEPENDENT STRUCTURES INC P O BOX 491655 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 438,201.50 241,891.50 2.a. Extra Work 14,750.00 14,750.00 b. Adjustment Comp. -500.00 -500.00 3. Materials on Hand 4. Earned Subject to Retention 452,451.50 256,141.50 5. Mobilization 6. Total Work Completed 452,451.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 452,451.50 256,141.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 256,141.50