Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-294-09-50 03-4M7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-5-22.0/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-04-13 INDEPENDENT STRUCTURES INC P O BOX 491655 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 440,147.40 0.00 2.a. Extra Work 21,811.58 6,531.65 b. Adjustment Comp. -500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 461,458.98 6,531.65 5. Mobilization 6. Total Work Completed 461,458.98 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 451,458.98 6,531.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,531.65