Dept. of Trans. PROGRESS Serial No. Contract No. 14-300-09-18 03-4M8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 40% 03-NEV-80-21.2/28.1 Federal Project: IM-804(199) Progress payment No. 03 Payment period ending: 10-20-14 ACME CONCRETE PAVING INC, DBA ACPI 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,737,071.00 826,019.61 2.a. Extra Work b. Adjustment Comp. -10,555.50 -52,917.06 3. Materials on Hand 4. Earned Subject to Retention 1,726,515.50 773,102.55 5. Mobilization 6. Total Work Completed 1,726,515.50 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,725,515.50 772,102.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 772,102.55