Dept. of Trans. PROGRESS Serial No. Contract No. 14-358-07-45 03-4M8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 48% 03-NEV-80-21.2/28.1 Federal Project: IM-804(199) Progress payment No. 05 Payment period ending: 12-18-14 ACME CONCRETE PAVING INC, DBA ACPI 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,362,139.66 94,352.47 2.a. Extra Work 5,419.49 5,419.49 b. Adjustment Comp. -43,682.44 -33,126.94 3. Materials on Hand 4. Earned Subject to Retention 2,323,876.71 66,645.02 5. Mobilization 6. Total Work Completed 2,323,876.71 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,323,876.71 66,645.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,645.02