Dept. of Trans. PROGRESS Serial No. Contract No. 15-265-10-12 03-4M8404 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 99% Location: Federal Project: 03-NEV-80-21.2/28.1 IM-804(199) Progress payment No. 010 Payment period ending: 09-20-15 ACME CONCRETE PAVING INC, DBA ACPI 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,386,067.91 427,483.79 2. a. Extra Work 70,196.60 0.00 b. Adustment Comp. -39,782.44 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,416,482.07 427,483.79 5. Mobilization 6. Total Work Completed 7,416,482.07 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,406,482.07 417,483.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 417,483.79