Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-011-14-36 03-4M8404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-80-21.2/28.1 IM-804(199) Progress payment No. 013 Payment period ending: 10-08-15 ACME CONCRETE PAVING INC, DBA ACPI 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,135,934.77 358,031.50 2. a. Extra Work 149,871.81 500.00 b. Adustment Comp. -39,782.44 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,246,024.14 358,531.50 5. Mobilization 6. Total Work Completed 8,246,024.14 7. Deductions 0.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,246,024.14 365,531.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,531.50