Dept. of Trans. PROGRESS Serial No. Contract No. 02-168-13-12 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 23% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 09 Payment period ending: 06-20-02 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,583,607.13 4,601,128.53 2.a. Extra Work 76,645.99 17,699.57 b. Adjustment Comp. 197,943.47 -32,544.46 3. Materials on Hand 9,524,622.29 522,562.22 4. Earned Subject to Retention 32,382,818.88 5,108,845.86 5. Mobilization 20,823,150.00 0.00 6. Total Work Completed 43,681,346.59 7. Deductions 8. a.Contract Retentions -3,238,281.89 -510,884.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 49,967,686.99 4,597,961.27 10. Reduction Amt to Escrow 11. Payment to Escrow 3,238,280.00 12. Net Pymt. this Estimate 4,597,961.27