Dept. of Trans. PROGRESS Serial No. Contract No. 02-232-14-02 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 29% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 11 Payment period ending: 08-20-02 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,884,728.91 5,046,932.74 2.a. Extra Work 569,172.01 58,931.69 b. Adjustment Comp. 171,402.31 -4,824.00 3. Materials on Hand 9,050,000.92 -1,435,072.84 4. Earned Subject to Retention 39,675,304.15 3,665,967.59 5. Mobilization 20,823,150.00 0.00 6. Total Work Completed 51,448,453.23 7. Deductions -12,044.00 -12,044.00 8. a.Contract Retentions -3,967,530.42 -366,596.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,518,879.73 3,287,326.83 10. Reduction Amt to Escrow 11. Payment to Escrow 3,967,530.00 12. Net Pymt. this Estimate 3,287,326.83