Dept. of Trans. PROGRESS Serial No. Contract No. 03-056-09-37 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 47% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 17 Payment period ending: 02-20-03 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,575,431.61 7,597,131.25 2.a. Extra Work 4,716,750.09 385,610.78 b. Adjustment Comp. 7,688,748.31 -3,584.00 3. Materials on Hand 9,195,267.11 -2,276,270.51 4. Earned Subject to Retention 70,176,197.12 5,702,887.52 5. Mobilization 26,375,990.00 0.00 6. Total Work Completed 87,356,920.01 7. Deductions -12,044.00 0.00 8. a.Contract Retentions -5,275,200.76 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 91,264,942.36 5,702,887.52 10. Reduction Amt to Escrow 11. Payment to Escrow 5,275,200.00 12. Net Pymt. this Estimate 5,702,887.52