Dept. of Trans. PROGRESS Serial No. Contract No. 03-357-16-07 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 77% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 28 Payment period ending: 12-20-03 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 83,375,598.44 3,176,764.29 2.a. Extra Work 19,564,099.84 486,188.14 b. Adjustment Comp. 57,378,488.31 5,963,694.00 3. Materials on Hand 14,277,084.39 3,590,489.40 4. Earned Subject to Retention 174,595,270.98 13,217,135.83 5. Mobilization 27,764,200.00 0.00 6. Total Work Completed 188,082,386.59 7. Deductions -42,044.00 0.00 8. a.Contract Retentions -8,729,763.55 -660,856.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 193,587,663.43 12,556,279.04 10. Reduction Amt to Escrow 11. Payment to Escrow 7,700,000.00 12. Net Pymt. this Estimate 12,556,279.04