Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-07-08 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 92% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 33 Payment period ending: 05-20-04 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 92,783,404.43 3,012,583.35 2.a. Extra Work 29,121,030.87 442,596.03 b. Adjustment Comp. 65,295,575.38 -4,196,289.68 3. Materials on Hand 47,987,465.82 12,970,285.77 4. Earned Subject to Retention 235,187,476.50 12,229,175.47 5. Mobilization 27,764,200.00 0.00 6. Total Work Completed 214,964,210.68 7. Deductions -39,594.00 0.00 8. a.Contract Retentions -11,759,373.83 -611,458.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 251,152,708.67 11,617,716.69 10. Reduction Amt to Escrow 11. Payment to Escrow 7,700,000.00 12. Net Pymt. this Estimate 11,617,716.69