Dept. of Trans. PROGRESS Serial No. Contract No. 04-205-09-23 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 49% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 35 Payment period ending: 07-20-04 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,025,391.59 10,150,498.39 2.a. Extra Work 29,164,762.77 43,731.90 b. Adjustment Comp. 172,453,555.45 -9,199,037.76 3. Materials on Hand 16,007,273.76 4,205,167.77 4. Earned Subject to Retention 323,650,983.57 5,200,360.30 5. Mobilization 27,764,200.00 0.00 6. Total Work Completed 335,407,909.81 7. Deductions -39,594.00 25,000,000.00 8. a.Contract Retentions -16,182,549.18 -260,018.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 335,193,040.39 29,940,342.28 10. Reduction Amt to Escrow 11. Payment to Escrow 7,700,000.00 12. Net Pymt. this Estimate 29,940,342.28