Dept. of Trans. PROGRESS Serial No. Contract No. 05-356-09-13 04-006034 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 75% 04-CC-680-24.9/25.5 Federal Project: 04-SOL-680-L0.1/0.7 ACIM-680-1(54) Progress payment No. 52 Payment period ending: 12-20-05 KIEWIT PACIFIC CO P O BOX 1769 VANCOUVER WA 98668 Escrow No. 01848 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,609,801.79 3,355,164.25 2.a. Extra Work 30,521,653.35 -3,267,239.86 b. Adjustment Comp. 315,925,676.71 13,706,412.90 3. Materials on Hand 4,137,138.07 -1,345,683.92 4. Earned Subject to Retention 552,194,269.92 12,448,653.37 5. Mobilization 27,764,200.00 0.00 6. Total Work Completed 575,821,331.85 7. Deductions -44,394.00 0.00 8. a.Contract Retentions -27,609,713.50 -622,432.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 552,304,362.42 11,826,220.70 10. Reduction Amt to Escrow 11. Payment to Escrow 9,986,750.00 12. Net Pymt. this Estimate 11,826,220.70