Dept. of Trans. PROGRESS Serial No. Contract No. 02-291-12-44 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 24% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 06 Payment period ending: 10-20-02 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,960,372.00 611,154.00 2.a. Extra Work b. Adjustment Comp. -1,443.20 -1,443.20 3. Materials on Hand 4. Earned Subject to Retention 2,958,928.80 609,710.80 5. Mobilization 6. Total Work Completed 2,958,928.80 7. Deductions -2,350.94 -2,350.94 8. a.Contract Retentions -295,892.88 -60,971.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,660,684.98 546,388.78 10. Reduction Amt to Escrow 11. Payment to Escrow 295,890.00 12. Net Pymt. this Estimate 546,388.78