Dept. of Trans. PROGRESS Serial No. Contract No. 02-324-12-44 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 28% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 07 Payment period ending: 11-20-02 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,393,387.00 1,433,015.00 2.a. Extra Work 26,052.23 26,052.23 b. Adjustment Comp. -1,731.84 -288.64 3. Materials on Hand 4. Earned Subject to Retention 4,417,707.39 1,458,778.59 5. Mobilization 6. Total Work Completed 4,417,707.39 7. Deductions -2,350.94 0.00 8. a.Contract Retentions -381,429.93 -85,537.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,033,926.52 1,373,241.54 10. Reduction Amt to Escrow 11. Payment to Escrow 381,420.00 12. Net Pymt. this Estimate 1,373,241.54