Dept. of Trans. PROGRESS Serial No. Contract No. 03-079-13-14 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 42% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 11 Payment period ending: 03-20-03 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,908,802.50 452,458.50 2.a. Extra Work 27,891.50 1,839.27 b. Adjustment Comp. -3,175.04 -288.64 3. Materials on Hand 4. Earned Subject to Retention 5,933,518.96 454,009.13 5. Mobilization 6. Total Work Completed 5,933,518.96 7. Deductions -115,392.94 -113,042.00 8. a.Contract Retentions -381,429.93 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,436,696.09 340,967.13 10. Reduction Amt to Escrow 11. Payment to Escrow 381,420.00 12. Net Pymt. this Estimate 340,967.13